Payment: T/T, 40% as deposit after signing contract, 60% balance to be paid before shipment.

Warranty: 3 years; one year for auxiliary machine; lifetime maintenance and technical service.

Delivery Plan:

Drawings Design

2days(deposit first)

Technical Department make tanks drawings, and send to buyer for confirmation.

Production Time

1day

1. Making purchasing&production plan;

2. Meeting with technical department, purchase department and production department, to confirm all details.

30-50days

1. Purchasing material and fittings;

2. Tanks body cutting, welding, polishing, trepanning;

3. Inner wall production;

4. Jacket preparation;

5. Pressure testing for inner tanks(welding testing by water for 60hours; jacket pressure testing by 4bar for 48hours.)

6. Outer wall production;

7. Pipes connection;

..........etc.

Leakage testing for whole tanks by 4bar gas for 48hours at least.

2days

Checked by QC department; and installation engineer clarify accessories, and finish.

Booking ship & packaging tanks

2days

Booking ship after balance payment and packaging all equipment. (we can send photos/video before your payment.)

Shipment

7-50days, depends on destionation port

From factory to destination port

Installation(if needed)

20-25days

Our engineer arrive your place to install the full set of brewery equipment, after the equipment arrive at your place. 